Upper hewakhola Hydropower Project(8.5MW)

Nov 12, 2021
Upper hewakhola Hydropower Project(8.5MW)

Development + Construction Period 1+2 years
Base Cost of the Project NRs 1,137.213 million (without IDC)
Loan/Equity Ratio 70:30
Loan Interest Rate 13%
Total Cost of Project with Financing 1,278.816 million
(With Interest During Construction)
IRR 15.75%
B/C Ratio 1.22
EIRR 21.37%
Simple Payback Period 5.43 years
Cost per kW US $ 1690 (1 US $ = NRs. 89)